PIERCE COUNTY TERMINAL BUILDING

Tacoma, Washington
Owner: Port of Tacoma
Project Cost $210 million
This
project included construction of a container yard, an intermodal yard,
infrastructure, utilities relocation, roadway work, traffic revisions,
and waterway and turning basin widening. The new Evergreen Terminal is
the largest construction project in the Port's 85-year history at an
estimated construction cost of $210 million. ORA was engaged to provide
complete testing and inspection services for the project that included
the Administration Building, Generator Building, Main Guard Building,
Maintenance Building, Marine Building, Reefer Wash, Roadability, Strad
Wash, Trouble Shack, and West Guard Building. Items of special
inspection and materials testing performed include: soils compaction,
reinforced concrete, reinforced masonry, structural steel, high strength
bolting, and spray-applied fireproofing.
2002
AIRFIELD IMPROVEMENT PROJECT - CONTRACTS 1 & 2
SeaTac, Washington
Owner: Port of Seattle
Contract 1 was performed under 2 work
orders – Taxiway B/ Taxiway North Reconstruction and Runway 16R – 34L
Pavement Repair. ORA provided testing and inspection of asphalt paving,
soils compaction, reinforced concrete, drilled core thickness
measurement. Contract 2 involved the testing and inspection of concrete,
structural steel, soils compaction, and asphalt paving under 6 work
orders – STEP Apron Pavement Construction, Concourse “A” Fuel Hydrant
System Phase I, Transiplex Hardstand Expansion, West Ramp South
Expansion, Perimeter Road/ AOA Fence Relocate, and Aircraft Fueling
System.
SEA AIR TRAFFIC CONTROL TOWER

Seattle, Washington
Owner: Federal Aviation Administration Seattle Center
Project Cost: $26 million
Supporting the FAA Seattle Center air traffic control operations, this project incorporates a complete
replacement airport traffic control tower and the establishment of an administrative base building at Seattle-Tacoma
International Airport. Otto Rosenau & Associates, Inc. was involved in the construction inspection and material
testing of all structural components including: soils, reinforced concrete, glass fiber reinforced concrete panel
fabrication, structural steel fabrication, and other duties.
TERMINAL 115 BERTH 1 MODIFICATIONS

Seattle, Washington
Owner: Port of Seattle
This project involved the alteration
of existing piers and construction of a new ramp into the Duwamish
Waterway including dolphins, winches, dredging and sheet piles. Our
structural special inspection scope of work included the following items:
reinforced concrete, shoring system welding, structural steel embedments
in concrete, and structural steel fabrication and erection (including
nondestructive testing of welds).
SFO INTERNATIONAL TERMINAL EXPANSION

San Francisco, California
Owner: SFO
Size: 1.8 million sq ft
Project Cost $103.7 million
Major expansion of the San Francisco International Airport. Contract services included all off-site
structural steel fabrication and all on-site structural steel erection for the complete structural steel
package. Structural steel fabrication was performed at multiple facilities including the Herrick Company
(Stockton Steel), San Bernardino Steel, PDM Strocal, Canron Portland and British Columbia, and Corey S.A.
in the State of Jalisco, Guadalajara, Mexico.
ORA was engaged to perform all structural steel fabrication inspections at the Canron New Westminster
facility (British Columbia, Canada), and included all material identification and mill certifications,
welder qualification and certifications, weld procedure specifications (WPS) review and approval, fitup,
preheating and post heating, welding of complete penetration and single/multiple pass welds, nondestructive
testing (Ultrasonic, Magnetic Particle and Liquid Penetrant Methods), high strength bolts and shop
application of two-part epoxy finishes.
ANC TERMINAL C REDEVELOPMENT

Anchorage, Alaska
Owner: City of Anchorage
Project Cost: 103.7 million
Major renovation to the Anchorage International Airport in Alaska. Contract services included all offshore
structural steel fabrication for the complete structural steel package. Structural steel was fabricated at the
facilities of Hyundai Heavy Industries, South Korea. Specific duties include material identification and mill
certifications, welder qualification and certifications, weld procedure specifications (WPS) review and
approval, fitup, preheating and post heating, welding of complete penetration and single/multiple pass welds,
nondestructive testing (Ultrasonic, Magnetic Particle and Liquid Penetrant Methods), high strength bolts and
shop application of two-part epoxy finishes.
|